0-5 years of experience
Managed, designed, and installed instrumentation and electrical capital projects for the division central engineering. Managed budgets ranging from $25,000 to $250,000. Duties included coordinating electrical and instrumentation design needs of site production units, specification of control systems, instrumentation & electrical equipment, design of instrument loops & electrical schematics, updating process PI&Ds & electrical one line diagrams, and coordinating & supervising project start-ups.
- Served as Instrumentation Engineer and lead Electrical Engineer on DCS upgrade and facility upgrade of Diazion toll unit. Managed electrical portion of approximately $100,000. Project included the installation of GSE DCS, Modicon Quantum PLC, Elcon intrinsically safe barriers, Powerware 65 kVA 480 Vac UPS, computer ground system, two 5-ton HVAC units, and the upgrade of 1000 instrumentation loops. Project completed on compressed time schedule, under budget, and boosted production rates by 10%.
- Designed and specified instrumentation and control loops for Tinuvin Production Capacity Increase Project. Project included the installation of Modicon PLC, GSE DCS, Elcon IS barriers, computer watch dog controls, transmitter upgrades, Ohmart radar level devices, control valve sizing, relief valve sizing, regulator sizing, and loop design. Project budget was approximately $9 Million.
- Provided engineering and design for Additives Granulation “Omega” Extrusion Project. Installation included Smar transmitters, Modicon PLC, Elcon IS Barriers, control system cabinet design, and HVAC controls.
- Designed and installed six IPM Inc. 10 kVA, 480 Vac UPS’s for emergency lighting upgrade for herbicide production unit. Served as Project Manager with budget of $150,000.
0-5 years of experience
Worked on various projects with Chevron Pipeline Company USA, Chevron Texaco USA, TEPPCO USA, ExxonMobil Inc. and Kinder Morgan Pipeline Company USA.
- Engineered and designed pipelines, petroleum storage and loading terminal facilities involving hydrocarbon measurement systems, additive injection systems and terminal automation control system.
- Integrated complex control systems, communication systems and flow measurement systems for monitor and control of pipeline, storage and loading terminals.
- Developed electrical and instrumentation engineering design package, including electrical and instrument plot plans, electrical area classification drawings, lighting and grounding layout drawings, schematics, loop drawings, wiring diagrams, conduit and cable routing, instrument index, schedules.
- Evaluated field-installed electrical equipment for possible hazard condition and developed electrical classification drawings per API and NFPA.
- Equipment and instrument specification, control narrative, cause and effect diagrams. Performed engineering calculations.
- Hands on ladder logic programming experience working with Allen Bradley SLC -500 and Micrologix 1000 PLCs & Troubleshooting of PLC programs used in terminal automation system.
- Operator interface panel layout and design exposure working with Allen Bradley Panel builder 32 programming software
- Performed startup and provided field support for petroleum storage and loading terminal automation systems.
6-10 years of experience
Programmed logic controllers for process equipment automation.
- Executed capital project checkout and startup.
- Developed front-end bid packages; performed project estimating, scheduling, and purchasing using SAP software.
- Developed electrical equipment specifications, process instrument specifications, and instrument databases.
- Procured electrical equipment and process instruments.
- Designed control panels and lighting panels.
- Developed electrical one-line diagrams and electrical schematics.
0-5 years of experience
Responsibilities included project management, electrical and instrumentation design, purchasing equipment, writing specs., obtaining and evaluating bids, training junior engineers, developing standards, overseeing contractor’s work. Responsible for nine jobs worth approximately $2 million. Served on the company energy control and management board for electricity purchase and generation. This included managing load additions, rebuilding of the generator control panels and updating single-line drawings. Included in my responsibilities was managing the upgrading of motor control rooms to meet OSHA and NEC requirements.
- Installed new emergency communications system combined with fire alarm systems; saved company by combining.
- Installed fire detection system based on radio rather than hard wiring; saved
- Saved $40,000 by relocating substation to meet clearance requirements while upgrading transformer to remove PCB’s.
0-5 years of experience
Lead engineer on projects ranging from $250K to $5 million.
- Created man hour estimates and material take offs.
- Mentored junior engineers and designers.
- Specified instrumentation and electrical equipment.
- Designed electrical schematics and power distribution systems
- Visited refineries and petrochemical plants to gather data for projects.
- Prepared weekly project reports for management.
0-5 years of experience
Secunded to Merck Sharp and Dohme for a Bulk Pharmaceutical Project.
- Participated in commissioning and start-up of dry and wet plant including high voltage switchgear 6.6 KV chiller, steam boiler, compressors, centrifuge, cooling tower, water treatment system.
- Supported start up activities for building heating, ventilating and HVAC and large process control system utilizing DDC and DCS control.
- Generate document detailing maintenance task and supported validation such as IQ, OQ and MCQ for GMP’s compliance. Then secunded to Wyeth – Ayerst Pharmaceutical plant for the commissioning and start up activities.